Maintenance Depot and Railway Sidings, Manchester

 

Historic operations had resulted in the significant impact of the underlying shallow groundwater by a range of hydrocarbons and PCB’s.
These contaminants were entering the sewer system in an uncontrollable manner.
The sewer entry point was sealed and the flow diverted through a temporary water treatment plant to remove the contaminants before being re-introduced to the sewer system under a consent to discharge.

Client

Rail company
Site
Maintenance depot and railway sidings, Manchester
Problem
PCB, Heavy oils and hydrocarbon contamination of groundwater
Technologies utilised
Phase separation, suspended solids removal, flocculent dosing, GAC Filtration, Process Control
Remediation criteria
Meet consent to discharge criteria
Validation
Project managed and validated by independent consultancy on behalf of the client